The project consists of 10 houses in total, including 8 17-storey buildings, 1 18-storey building, 1 15-storey high-rise residential building, 2 1-storey power stations, 1 1-storey garbage station and 1 first-floor supporting facilities. The total construction area is 103829.3. M2.

ce0200cd12bb444cae708608718b8c09

Highlights

In accordance with the requirements of the standardization of Linjian Construction of Shanghai and China Construction Eighth Bureau, the project is equipped with temporary facilities such as box-type houses, fabricated enclosures and access control systems.

9105f40346164397a92c424de71a6461

The face recognition system and the tower crane anti-climbing device are arranged to prevent the operation of non-designated drivers in the management of large equipment such as tower cranes and construction elevators, and the anti-collision system installed in the group tower operation monitors the running state of the tower crane in real time.

61a5a5133baa4faf95356811c1f5080c

In terms of safety publicity and warning, the project has set up a safety publicity corridor on the main safety channel of the construction site, and configured a dangerous source electronic display screen at the eye-catching position on the site, and a voice safety broadcaster is installed in the dangerous area and the main operation surface entrance and exit.

In the dust control, automatic spray dust reduction system is installed on both sides of the construction road and around the floor, and automatic dust-reducing equipment such as fog guns are arranged on site; environmental detection devices are set up, emergency plans are started according to air pollution warning response level, and air pollution emergency measures bulletin board is suspended.

In terms of fire management, the project is equipped with a fire-fighting vehicle in addition to adequate fire-fighting facilities to prevent emergency use of emergencies.

Shape management. An air-energy water heater is used for the bath to ensure hot water supply for 24 hours.xx